Scheduled power interruption affecting parts of Pampanga on Sunday, 25 October 2026. Time: 3:00AM - 7:00AM Affected: PELCO III ( PELCO III ) (Pao, Apalit, Macabebe & Masantol Substations) Reasons: To facilitate dismantling activities along the Marilao-Hermosa 230kV Line as part of the transmission line relocation and modification works affected by the proposed DPWH NLEX Sto. Tomas Exit Project along Mexico-Calumpit 69kV Line. Specific areas are determined by the electric cooperative. NGCP will exert all efforts to restore power earlier or as scheduled. #NGCP See less