CENPELCO POWER ADVISORY
POWER SERVICE INTERRUPTION NOTE
DATE AND TIME:
A. October 21, 2026 (Wednesday) 8:00 AM to 5:00 PM
B. October 22, 2026 (Thursday) 9:00 AM to 12:00 NN
C. October 22, 2026 (Thursday) 10:00 AM to 4:00 PM
D. October 23, 2026 (Friday) 8:00 AM to 5:00 PM
E. October 23, 2026 (Friday) 8:00 AM to 5:00 PM
AFFECTED AREAS:
A. PORTION OF SAN CARLOS CITY (AREA XI - SOUTH) - Balite Sur, Sitio Sagur
B. PORTION OF MALASIQUI - Portion of Lepa, Palong Baleg, Portion of Melag
C. PORTION OF MALASIQUI - Taloyan, Balite
D. PORTION OF MALASIQUI - Palapar Sur, Bongar
E. PORTION OF MALASIQUI - Portion of Nalsian Norte - Baleno, Leet, Karel, Project 4, Portion of Warey - Baleno
PURPOSE:
A. Relocation of pole, transfer pole metering.
B. Installation of additional distribution transformer.
C. Installation of intermediate pole, right of way clearing, replacement of bare ACSR #2 to 23kV poly.
D. Replacement of rotten pole, right of way clearing, relocation of pole, clustering of kwhr meters.
E. Replacement of rotten pole, right of way clearing, extension of 1-ph line, installation of additional distribution transformer.
City Information Office San Carlos City Pangasinan
ASenso Malasiqui
We may energize the lines ahead the allotted time. Therefore, please consider the lines and equipment energized at all times.
We apologize for the inconvenience due to the corrective maintenance activities. See less